What actually threatens completion?

Review procurement events against programme dependencies, available float, and downstream activities to assess which delays may be absorbed — and which may affect completion.

01

PROCUREMENT EVENT

02

DEPENDENCY

03

FLOAT

04

CASCADE

05

COMPLETION

The problem

A delay is not the same thing as programme impact.

Two suppliers can report similar delays while creating completely different consequences. The difference is where each event sits in the programme, how much float remains, and what downstream work depends on it.

DELAY A

Facade panels

+14 days

AVAILABLE FLOAT

6 weeks

PROGRAMME EXPOSURE

Low

DELAY B

Structural steel

+7 days

AVAILABLE FLOAT

0 days

PROGRAMME EXPOSURE

High

The number of days lost is not enough to understand the risk. The question is where those days sit in the programme.

The programme ripple

Follow one procurement event through the work it can affect.

A supplier event becomes useful information when it is connected to the activities downstream.

PROCUREMENT EVENT

Switchgear delivery

Supplier reports a 7-day movement.

EVENT MOVEMENT

+7 days

Electrical installation

SUCCESSOR ACTIVITY

0d float

Testing & commissioning

SUCCESSOR ACTIVITY

3d float

Services completion

SUCCESSOR ACTIVITY

5d float

Practical completion

SUCCESSOR ACTIVITY

Exposure

What MorrnIx evaluates

Four questions before a procurement issue becomes a programme problem.

DEPENDENCY

What depends on it?

Connect the procurement event to the construction activity or milestone it affects.

FLOAT

How much flexibility remains?

Separate a delay that can be absorbed from one consuming the programme's available float.

CASCADE

What moves next?

Trace affected successor activities instead of treating every supplier delay in isolation.

CONSEQUENCE

Does completion move?

Surface whether the event creates meaningful programme exposure and needs attention.

Programme exposure

Not every delay deserves the same response.

ABSORBABLE

Delay+10d delay
Float+18d float

No current programme impact

NEAR-CRITICAL

Delay+7d delay
Float+5d float

Programme exposure emerging

CRITICAL

Delay+3d delay
Float0d float

Immediate attention required

How it works

Map the programme. Correlate the procurement. Test the consequence.

01

Map

Establish the relevant programme activities, milestones, dependencies and procurement dates.

02

Correlate

Connect supplier commitments and emerging procurement issues to the activities they affect.

03

Test

Assess float, successor relationships and the potential downstream effect of the event.

04

Prioritise

Surface procurement issues based on actual programme exposure, not generic urgency.

In practice

A supplier delay becomes useful information when it is put against the programme.

Illustrative example based on the workflow we are validating — not a specific named client engagement.

SUPPLIER EVENT

Switchgear delivery moves

The supplier reports a 7-day movement against the current commitment.

+7 days

PROGRAMME CORRELATION

Required-on-site dateWeek 18
Electrical installation2d available float
CommissioningDownstream dependency
Current finding5d potential exposure

The finding is not simply that the supplier is late. It is that the remaining programme flexibility may not absorb the movement.

Programmes change

The programme you analysed last week may not be the programme you are managing today.

When sequencing, acceleration, scope or other programme logic changes, exposure can move with it. Impact needs to be re-correlated against the current programme.

WEEK 12

Steel

Critical activity

WEEK 16

Facade

Critical activity

WEEK 20

Commissioning

Critical activity

Who this is for

Built for the people deciding what gets attention.

Project Manager

“Which procurement issue can actually move my completion date?”

Construction Manager

“Which delayed item affects the next workfront?”

Planner / Project Controls

“Where is float being consumed?”

Project Director

“Which risks can become programme problems?”

Today and tomorrow

Manual programme correlation today. Connected intelligence tomorrow.

Today

We receive the current programme and procurement information, then manually connect supplier events to relevant activities, float and programme exposure.

Tomorrow

A future connected platform could relate procurement commitments and programme changes to the latest schedule. Today, this service uses manual review to relate the supplied information to relevant activities, float, and potential exposure.

Know what procurement risk needs attention.

Explore our research-led approach to procurement risk. Monitoring is currently human-led while the MorrnIx platform is being developed.